With capacity reached at the current brewhouse, Copper Dragon is looking to expand once again in 2008.

After many months of searching for a suitable site in Skipton. Land and buildings became available and Copper Dragon was fortunate to secure them. The very important water supply remains the same.

The new site will be built in three phases, with the first building being allocated for the new brewhouse and fermentation room,

The entire plant will be Steam Powered combined both the best of the old world and with technology from today.

Construction of the new brewhouse is now complete and with the plant now fully commissioned.


DRAWING-D.jpg
Grain storage system

DRAWING-C.jpg
Kettle with external colandria

Architect-drawing.jpg
An artist impression of the proposed new brewery